The progress report of IRID and JAEA on subsidy program (the Seventh solicitation) for the” Project of Decommissioning and Contaminated Water Management (Full-scale Test for Repairing Leaks from PCV and Water Stoppage of PCV)” in the FY2013 Supplementary Budget [Released on May 29, 2015]

The progress report of subsidy program (the Seventh solicitation) for the” Project of Decommissioning and Contaminated Water Management (Full-scale Test for Repairing Leaks from PCV and Water Stoppage of PCV)” in the FY2013 Supplementary Budget are as follows.

  • Progress outolines
  • Materials (February 26,2017) from Secretariat meeting / Decommissioning and Contaminated Water team meeting of Ministry of Economy, Trade and Industry
    Reference materials: (2-②-2) Full-scale Test for Repairing Leaks from PCV and Water Stoppage of PCV

    International Research Institute for Nuclear Decommissioning, Japan Atomic Energy Agency (Joint Proposal)
    [Japanese text only]