IRID’s summary results of subsidy program (the Second solicitation) for the” Project of Decommissioning and Contaminated Water Management (Project of Upgrading Approach and System for Retrieval of Fuel Debris and Internal Structures (FY2015))” in the FY2014 Supplementary Budget [Released on January 26, 2023]
The summary results of subsidy program (the Second solicitation) for the” Project of Decommissioning and Contaminated Water Management (Upgrading Approach and System for Retrieval of Fuel Debris and Internal Structures)” in the FY2017/18 Supplementary Budget are as follows.
- Upgrading Approach and System for Retrieval of Fuell Debris and Internal Structures (FY2015)
International Research Institute for Nuclear Decommissioning
[Japanese text only]